Conclusion
1. Describe the problems that would result from ordering too much concrete.
Estimating the cost with too much concrete would inflate the price of the project; thus making the the client less likely to agree to the proposal, , whilst wasting material.
2. Describe the problems that would result from ordering too little concrete.
You will not have enough material to make the building, and to assure that it is structurally sound.
3. What percentage of the total cost of the pad does the steel rebar account for?
It accounts for roughly one quarter of the cost.
4. Why is it important to estimate the cost of construction for a building project?
To know whether or not it is worth pursuing that design, and to see if it falls within the budget set forth by the client.
1. Describe the problems that would result from ordering too much concrete.
Estimating the cost with too much concrete would inflate the price of the project; thus making the the client less likely to agree to the proposal, , whilst wasting material.
2. Describe the problems that would result from ordering too little concrete.
You will not have enough material to make the building, and to assure that it is structurally sound.
3. What percentage of the total cost of the pad does the steel rebar account for?
It accounts for roughly one quarter of the cost.
4. Why is it important to estimate the cost of construction for a building project?
To know whether or not it is worth pursuing that design, and to see if it falls within the budget set forth by the client.